Relocation of a 50m High Wind Mast in Marsabit

Client: Kengen
Type: Sub-Contract
Duration: September 2010

Scope of Works:

Relocation of an existing 50m high Wind Mast at Marsabit
The work included the following:
  • Dismantling, transport and re-erection of the mast
  • New foundation works for the mast
  • Dismantling and re-installation of Data Loggers
  • Dismantling and re-installation Anemometers
  • Dismantling and re-installation Wind Direction Vanes
  • Dismantling and re-installation Temperature sensor
  • Dismantling and re-installation of the equipment accessories